Scheduled Maintenance - Network maintenance 11/05/22 12-06am
完了
2022年05月11日 06:00 NZST
開始
2022年05月11日 00:00 NZST
スケジュールのメンテナンス
2022年05月11日 00:00–06:00 NZST
Summary
During this outage window maintenance will be performed on two of our Handover links. There are expected to be up to three 10 minute outages per service
Outage Window
Planned start date: 12/05/2022 00:05:00 NZST (2022-05-11 12:05:00 UTC)
Planned end date: 12/05/2022 06:00:00 NZST (2022-05-11 18:00:00 UTC)
Planned duration: 30 Minutes
Service Impact
Enable Fibre - Christchurch
Tuatahi First Fibre (UFF) - Hamilton
Customer Impact
Customers may lose connection during each outage period