Scheduled Outage - MDR phase 2 – 19/05 – 1:00 am to 5:00 am
Endte
May 19, 2020 3:07 AM NZST
Løst
May 19, 2020 3:07 AM NZST
This upgrade has already finished.
Startet
May 19, 2020 1:00 AM NZST
Planlagt
May 19, 2020 1:00 AM–3:07 AM NZST
Summary
During this outage we will be updating the firmware on our routers to resolve a known issue in data reporting
Outage Window
19/05 1:00 am to 19/05 5:00 am
Service Impact
All NGA customers (expect Napier)
Upstream connection
Grafton/Orewa Office and PoP customers
Customer Impact
There will be up to 40 minutes outage during the maintenance time window for All Fibre (expect Napier) and Grafton/Prewa PoPs customers